Contract Award Notice Details
Contractor Name Momentum Trains Pty Ltd
ACN 630634507
ABN
75 630 634 507
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 19 177 Pacific Hwy
Town/City North Sydney
State/Territory NSW
Postcode 2060
Country AUSTRALIA
Related RFT ID
ISD-17-6185
The main private sector parties are:
Momentum Trains (Project Co)
Designated Investors
- Pacific Partnerships Pty Ltd (ABN 85 601 328 741)
- CAF Investment Projects S.A. (NIF A78581550)
- DIF Infrastructure V Cooperatief U.A. (KvK 68027982)
Key Subcontractors and Key Subcontractor Guarantors
a) Construcciones y Auxillar de Ferrocarriles S.A (NIF A20001020) (Delivery Subcontractor). Project Co has subcontracted its obligations to design and construct the RRP Works to the Delivery Subcontractor under the Delivery Subcontract. The Delivery Subcontractor has also entered into an associated side contract with Transport for NSW and RailCorp.
b) UGL Rail Services Pty Ltd (ABN 58 000 003 136) (Maintenance Subcontractor). Project Co has subcontracted its obligations to maintain the Delivered Rail Assets to the Maintenance Subcontractor under the Maintenance Subcontract. The Maintenance Subcontractor has also entered into an associated side contract with Transport for NSW and RailCorp.
c) CIMIC Group Limited (ABN 57 004 482 982) (Maintenance Subcontract Guarantor). This guarantor has entered into a parent company guarantee with Project Co to guarantee certain liabilities and obligations of the Maintenance Subcontractor.
Depot Subcontractor
CPB Contractors Pty Ltd (ABN 98 000 893 667). The Delivery Subcontractor has subcontracted its obligations to design and construct the Maintenance Facility to the Depot Subcontractor under the Depot Subcontract. The Depot Subcontractor has also entered into an associated side contract with Transport for NSW
Design Consultant
WSP Australia Pty Limited (ABN 80 078 004 798). The Depot Subcontractor has subcontracted its obligations to design the Maintenance Facility to the Design Consultant under the Design Consultant Engagement. The Design Consultant has also entered into an associated side contract with Transport for NSW and RailCorp.
Independent Certifier
APP Corporation Pty Ltd (ABN 29 003 764 770) has been jointly engaged by Transport for NSW, RailCorp and Project Co to carry out independent certification services in relation to the RRP Works.
Debt Financing Parties
MUFG Bank, Ltd (ARBN 103 418 882) has been engaged by Project Co as the Security Trustee.
$1,176,686,000.00 (A project to be undertaken)
$1,210,649,391.36 (A project to be undertaken)
The contract provides for:
- Monthly Service Payments over the maintenance phase;
- Conditional debt pay down; and
- Expiry payment
Multi-Stage
The Monthly Service Payment is calculated in accordance with clause 1 of Schedule 16 to the Regional Rail Project Deed and includes the following:
- Availability Payment;
- Indexation;
- Maintenance Payment;
- Volume Adjustment;
- Marginal Unit Adjustment Payment;
- Insurance Adjustment;
- Additional Maintenance Service Payment;
- Monthly Service Payment Adjustment; and
- Base Interest Rate Adjustment
The Monthly Service Payment Adjustment is calculated in accordance with clause 1 of Schedule 17 to the Regional Rail Project Deed and includes the following:
- Availability Adjustment;
- Cancelation Adjustment;
- Delay Adjustment;
- KPI Adjustment;
- Transition-in Adjustment;
- Simulator Adjustment;
- Reliability Adjustment;
- Recovery Services Adjustment;
- Final Acceptance Deduction;
- Fleet Acceptance Deduction;
- Energy Adjustment;
- Jobs, Skills and Industry Participation Adjustment;
- Environment and Sustainability Adjustment; and
- Train Completion Works Adjustment
Payments to the contractor may be varied if any of the Option Units or Additional Option Items in Schedule 44 and Schedule 44A of the Project Deed are exercised.
Transport for NSW may modify the Regional Rail Project Deed requirements relating to Project Co’s activities. The Regional Rail Project Deed gives Transport for NSW the right to require Project Co to carry out the following categories of Modifications:
- Modifications;
- Change in Mandatory Requirements;
- Minor Modifications; and
- Configurable Item Changes
Project Co may propose a Modification to the Regional Rail Project Deed. Transport for NSW has absolute discretion to approve or reject the proposed Modification.
Clause 39 provides that Transport for NSW may modify the Regional Rail Project Deed requirements relating to Project Co’s activities
Clause 4 provides that Transport for NSW may extend the term of the contract for up to four further five year periods.
Clause 58 Assignment and amendments.
Summary of the criteria against which the various tenders were assessed
Evaluation Criteria | Weighting |
---|---|
The RFP Evaluation Criteria encompass the following specific consideration:
|
No
Refer to "Other private sector entities involved in, with an interest in or benefiting from this contract" for details of Delivery Subcontractor, Maintenance Subcontractor, Depot Subcontractor and Design Consultant.
Not Applicable
Not Applicable
Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW
State/Territory NSW
Country AUSTRALIA
Email Address ProcurementTeamContractDisclosure@transport.nsw.gov.au
The disclosed contract value represents the contract price, including variations (if applicable) plus an additional 10% for GST. This value may be overstated if GST does not apply to [all parts of] the contract.
All fixtures affixed to the Maintenance Facility Site, the Legacy Maintenance Centre or a Stabling Yard will be owned by Transport for NSW or RailCorp from the time they are affixed.
Ownership of all Delivered Rail Assets transfers to RailCorp on the relevant Date of Provisional Acceptance of the Asset or, for all Equipment, Spares, Consumables and Special Tools, the earliest of the date Project Co or its Key Subcontractor acquires title to the relevant item and the date on which the item is delivered to a Site.
Not applicable.
Commercial in confidence.
Please see the Project Summary which will be made available on the Treasury website at a later date.
The full base case financial model is commercial in confidence.
Please see the Project Summary which will be made available on the Treasury website at a later date.
The State guarantees the performance of TfNSW's payment obligations under the Regional Rail Project Deed and other documents related to the project.
Refer to the published copy of the Regional Rail Project Deed which will be available on TfNSW's website at a later date.
Please see the Redaction Schedule for this contract which is published on the TfNSW website:
Please see the Redaction Schedule for this contract which is published on the TfNSW website:
Please see the Redaction Schedule for this contract which is published on the TfNSW website: