Contract Award Notice Details
Contractor Name ADCO Constructions Pty Ltd
ACN 001044391
ABN
46 001 044 391
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 2, 7-9 West Street
Town/City North Sydney
State/Territory NSW
Postcode 2060
Country AUSTRALIA
Not Applicable
$13,595,041.90 (A project to be undertaken)
$14,684,309.25 (A project to be undertaken)
Not Applicable
Multi-Stage
TfNSW Medium Works Contract
- Clause 6 - Variations
- Schedule 10 - Prices and Rates for valuation of Variations and Overhead Costs
Not Applicable
Summary of the criteria against which the various tenders were assessed
Evaluation Criteria | Weighting |
---|---|
Project Delivery Methodology |
17.5% |
Project Program |
17.5% |
Relevance of expertise and experience of key personnel (including designers), availability and current workload |
15% |
Price |
50% |
No
Not Applicable
Not Applicable
Not Applicable
Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW
State/Territory NSW
Country AUSTRALIA
Email Address ProcurementTeamContractDisclosure@transport.nsw.gov.au
The Contract has been awarded under the existing Multi-Storey and At-Grade Car Parks Framework Deed IPD-20-8979 with ADCO which was executed on 21 January 2021.
The Principal can accept a Quotation submitted by the Contractor under clause 1.4 of Annexure B to the Framework Deed IPD-20-8979 by issuing a Notice to Proceed letter to the Contractor.
Original contract amount: $12,359,129 (excl. GST)
Original contract end date: 17-Mar-2023
This contract has been varied.
- Variation 01: an additional $12,129.21 (excl. GST)
- Variation 02: an additional $7,454.09 (excl. GST)
- Variation 03: an additional $3,220 (excl. GST)
- Variation 04: an additional $18,135.50 (excl. GST)
- Variation 05: an addtional $7,133.14 (excl. GST)
- Variation 06: an additional $59,723 (excl. GST)
- Variation 08: an additional $10,131.50 (excl. GST)
- Variation 09: an additional $138,048.88 (excl. GST)
- Variation 10: an additional $37,360 (excl. GST)
- Variation 11: an additional $3,934.89 (excl. GST)
- Variation 12: an additional $228,507.81 (excl. GST)
- Variation 13: an additional $15,777.21 (excl. GST)
- Variation 14: an additional $20,125 (excl. GST)
- Variation 15: an additional $10,999.32 (excl. GST)
- Variation 16: an additional $8,726 (excl. GST)
- Variation 17: an additional $33,878.10 (excl. GST)
- Variation 18: an additional $55,884.37 (excl. GST)
- Variation 19: an additional $319,075.03 (excl. GST)
Extension of Time (EoT)
- EoT: revised Date for Completion of 18-Mar-2023
- EoT: revised Date for Completion of 23-Mar-2023
- EoT: revised Date for Completion of 05-May-2023
- EoT: revised Date for Completion of 13-May-2023
- EoT: revised Date for Completion of 31-May-2023
- EoT: revised Date for Completion of 31-Aug-2023
- EoT: revised Date for completion of 5-Oct-2023