Tender Details
This specification covers the installation of a cruciform shaped reinforced concrete footing to replace the existing concrete footings on Tower 105 of the Kemps Creek to Avon 330kV Transmission Line No.37. The work is required to prevent mine subsidence damage to the tower and the transmission line during longwall mining of an underlying coal seam.
Location
RFT Type
Additional Details / Instructions
A mandatory site inspection will be conducted on Monday 27th July, commencing at 10:30am.
Further details regarding the inspection may be obtained by contacting John Petrolo on Ph: (02) 9620 0737 or Mobile: 0438 250 778.
Address for Lodgement
See Quotation Form for Lodgement Details
Conditions for Participation
Tenders must be for the whole of the works specified and include all obligations set out in the Specification. Tenders for only part of the works will not be considered.
Tenderers shall attend a mandatory site inspection on Monday 27th July 2009 commencing at 10:30am at Tower 105 on Transmission Line 37.