Tender Details
This specification requires the repair, preparation and sealing of bunded areas at the following TransGrid Substations.-
Dapto 330 kV Substation, Ingleburn 330 kV Substation, Kemps Creek 500 kV Substation, Liverpool 330 kV Substation, Sydney East 330 kV Substation (Belrose) & Sydney North 330 kV Substation (Dural).
The works includes but is not limited to;
· Repair brick and/or mortar of bund walls
· Clean bund areas
· Inspect for cracks and repair
· Seal bund areas
Location
RFT Type
Additional Details / Instructions
The Tenderer shall attend all Mandatory Site Inspections to fully acquaint themselves with matters and conditions affecting the work.
Substation Date Time
Kemps Creek 500 kV S/S 15th September 2009 0730
Liverpool 330 kV S/S 15th September 2009 0930
Ingleburn 330 kV S/S 15th September 2009 1100
Dapto 330 kV S/S 15th September 2009 1330
Sydney East 330 kV S/S 16th September 2009 0800
Sydney North 330 kV S/S 16th September 2009 1000
The site inspection will be conducted by the Principal's representative Phil Kofler. Attendees are requested to register their attendance by contacting Phil Kofler on (02) 9620-0619 or by e-mail to phil.kofler@transgrid.com.au
Estimated Timeframe for Delivery
It is proposed to grant Possession of Site within two (2) weeks of the issue of the Principal’s Purchase Order.
Practical Completion for all works at all sites is twenty (20) weeks from the Possession of Site Date.